1) Roof Works
(2) Piping Works
(4) Fire seal penetrations on all floors
- Remove timber roof decking and replace with Aluminium sheeting
- Remove and reinstate Hot water units currently located on timber roof decking
(2) Piping Works
- Build three (3) new service hatches on each floor
- Cut new concrete core-holes in building floors, walls & install new pipe trays
- Install 45 sets of pipework to service units who do not presently have A/C installed
(4) Fire seal penetrations on all floors
Last edited: